Project Code Project Title Status Current Stage Project Manager Start Date Close Date
AV2951 Teaching Desk & Projector Upgrades 2022 In Progress Build Stephen Dishon 01-Feb-2022 29-Sep-2022
HSS006 ELTC Class.net Online Toolkit Suspended Build Sally Hayward 23-Jun-2014
AV2791 KB-Nucleus Project (NP) In Progress Build John Power 01-Jan-2019 01-Sep-2022
RSS048 Storage Manager Operational Transition In Progress Build Mike Wallis 13-Aug-2018 30-Nov-2022
RSS501 DataStore Fibre Channel Replacement In Progress Build Lawrence Stevenson 09-Aug-2022 30-Nov-2022
AV2943 EFI-Collaborative Teaching Space 2022 In Progress Build Stephen Dishon 25-Oct-2021 09-Sep-2022
AV2931 Hybrid Level 1 - Additional 1m SD Spaces Withdrawn Build David Whitaker 01-May-2021 30-Sep-2021
LUC056 UCF insurance claim project In Progress Build Christine Megowan 01-Apr-2021 14-Feb-2024
AV2932 Education - Hybridising Holyrood 2021 Suspended Build Stephen Carter 01-May-2021 30-Sep-2021
COM067 Wiki: Annual Upgrade In Progress Build Chris Konczak 13-Jan-2022 12-Aug-2022
AV2880 ECCI AV Room Upgrades In Progress Integrate Euan Thomson 01-Jun-2020 09-Sep-2022
RSS404 Large Scale Data Transport In Progress Integrate Lawrence Stevenson 22-Oct-2021 25-Nov-2022
AV2903 StEAP - CSE Lecture Recording Suspended Integrate Stephen Dishon 25-Jun-2020 17-Dec-2021
CIS014 Network Infrastructure Deployment In Progress Integrate Alan Gray 07-Jan-2019 30-Nov-2023
SAC085 GDPR 2 for student systems Suspended Analyse Franck Bergeret 01-Oct-2021 30-Jun-2022
DTI050 Finance Data Marts for Strategic Reporting Closed Analyse Ben Armstrong 20-Sep-2019 18-Feb-2022
TEL057 Learn Foundations Closed Analyse Lee-Ann Simpson 27-Aug-2018 18-Jan-2022
LTW003 Digital writing surfaces in Science and Engineering In Progress Analyse Victoria Dishon 08-Jan-2018 31-Jul-2018
SRA004 Future State In Progress Analyse Andy Donne 05-Sep-2019
AV2855 Outreach - B1.11-1,2 & 3 In Progress Analyse Guy Tittley 08-Oct-2019 16-Sep-2022
AV2976 ML-Careers Meeting Rooms In Progress Analyse Richard Leslie 01-Jun-2022 29-Jul-2022
AV2947 Thomson's Land + GT Hall Withdrawn Analyse Guy Tittley 01-Feb-2022 30-Sep-2022
AV2948 George Sq, 50, AV Upgrade, 2022 Withdrawn Analyse David Whitaker 25-Feb-2022 16-Sep-2022
AV2949 George Sq, 40, AV Upgrade, 2022 Withdrawn Analyse Euan Thomson 01-Feb-2022 16-Sep-2022
AV2966 Easter Bush 2022 Upgrades In Progress Analyse David Whitaker 02-May-2022 16-Sep-2022