- Report Date
- October 2019
Achievements in Last Period:
- Project Brief written, reviewed, revised and signed-off.
- Communications Plan written, reviewed and signed-off.
- Work has started on analysing and better understanding the first project objective of tightening access controls.
Issues:
Next Steps:
- Project resource to assess effort involved in tightening access controls on Office 365 Admin Accounts and engage with wider stakeholder group.
- Approved budget
- 100.0 days
- Activity this month
- 4.5 days
- Activity this year
- 7.0 days
- Activity to date
- 7.0 days
- Estimate to complete current year
- 93.0 days
- Estimate to complete future years
- 0.0 days
This article was published on