Report for June 2017
- Report Date
- June 2017
Achievements
The project brief has been completed and has been sent off for signing off to the Project Sponsor, Rhian Davies.
Issues
Brief has not been signed off.
PM has gone ahead and started interviewing Program and Portfolio Managers as part of the projects. These meetings were set up with the expectation that the brief would be signed off before the meetings.
Next Steps
Await sign off and continue doing interviews that are already arranged in diary.
Milestones
Target Date | Previous Date | Title |
---|---|---|
30-Jun-2017 | None | Finished Project Brief |
07-Jul-2017 | None | Finished report on current MI |
28-Jul-2017 | None | GAP Analysis complete |
11-Aug-2017 | None | Finished Research Report |
- Approved budget
- 8.0 days
- Activity this month
- 2.0 days
- Activity this year
- 2.0 days
- Activity to date
- 2.0 days
- Estimate to complete current year
- 6.0 days
- Estimate to complete future years
- 0.0 days