Report for June 2017

Report Date
June 2017

Achievements

The project brief has been completed and has been sent off for signing off to the Project Sponsor, Rhian Davies.

 

Issues

Brief has not been signed off.

PM has gone ahead and started interviewing Program and Portfolio Managers as part of the projects. These meetings were set up with the expectation that the brief would be signed off before the meetings.

 

Next Steps

Await sign off and continue doing interviews that are already arranged in diary.

 

Milestones

Target Date Previous Date Title
30-Jun-2017 None Finished Project Brief
07-Jul-2017 None Finished report on current MI
28-Jul-2017 None GAP Analysis complete
11-Aug-2017 None Finished Research Report

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
8.0 days
Activity this month
2.0 days
Activity this year
2.0 days
Activity to date
2.0 days
Estimate to complete current year
6.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Management Information Review
Code
P0298
Programme
Project Management Office (PMO)
Project Manager
Jialei Ding
Project Sponsor
Rhian Davies
Current Stage
Initiate
Status
In Progress
Start Date
26-Jun-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
25-Aug-2017
Overall Priority
Normal