Status report for period ending 13 March 2020

Report Date
March 2020

Key activities/milestones since last report

Key activities since last report

  • Completed revisions to DAS for PRC on 3 April 2020
  • DAS path to green review and action agreed - project scope and timescales clarified

Milestones achieved since last report

  • N/A

Key activities/milestones planned not delivered

Activities planned not delivered

  • Approval levels not linked to jobs as awaiting decisions to inform work on defining jobs and approval levels.

Milestones planned not delivered

  • RACI (DAS and approval levels) delayed due to PRC and Court consideration of DAS having been rescheduled and outstanding decisions relating to jobs and approval levels.
  • Impact assessment which will now be carried out by the Change and Implementation Team/Implementation groups will be carried out August 2020.

Upcoming activities/milestones

Upcoming activities

  • Continue defining DAS approval level codes for Oracle
  • Test approval levels and map to Oracle jobs for remaining schools/units
  • Revised DAS to go to Policy and Resources Committee 3 April 2020 and University Court 27 April 2020
  • Obtain resolution of outstanding decisions
  • Map out BAU process for ongoing control and maintenance of approvals framework
  • Develop communications plan

Upcoming milestones

  • DAS approved by Court - April 2020
  • Approval levels approved by Design Authority - April 2020
  • Impact assessment complete - August 2020
  • Approval levels linked to Oracle jobs complete - November 2020

Key risks and issues

Risks and issues for escalation

  • N/A

New/changed risks and issues for information

  • Ownership of the approvals framework and process for BAU maintenance and controls have not yet been considered - process to be mapped out
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Status changed to green following 'path to green' review and actions.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Delegated Authority Schedule and Governance (DAS)
Code
SEPFTP002
Programme
Service Excellence - Finance Transformation Programme (SEPFTP)
Management Office
Service Excellence PMO
Project Manager
Susan Mulhearn
Project Sponsor
Rachael Robertson
Current Stage
Execute
Status
In Progress
Start Date
20-Jun-2017
Planning Date
n/a
Delivery Date
30-Apr-2020
Close Date
n/a
Overall Priority
Normal

Documentation

Not available.