Report for January 2018
- Report Date
- January 2018
Achievements
- Commenced work on solutions to deliver Privacy Notices
- Original budget reduced
Issues
- Outstanding milestones revised
Next steps
- Continue discussions with other areas re Matriculation and Announcements
- Check delivery of solution with vendors
- Test delivered solution against requirements
Milestones
19-Feb-2018 | Build/development work completed | Build |
06-Mar-2018 | Acceptance sign-off | Accept |
15-Mar-2018 | Delivery of updates into Live [Provisional] | Deliver |
23-Mar-2018 | Delivery sign-off [Provisional] | Deliver |
23-Apr-2018 | Project closure [Provisional] | Close |
- Approved budget
- 40.0 days
- Activity this month
- 3.1 days
- Activity this year
- 22.1 days
- Activity to date
- 22.1 days
- Estimate to complete current year
- 17.5 days
- Estimate to complete future years
- 0.0 days