Report for December 2017

Report Date
December 2017

Achievements this period

  • Presented solution options document to Hope Park team including the sponsor and CIO - the team agreed there are some feasible options and are will now look to commission a follow-up project to take on the procurement and implementation activities
  • Followed up actions from solution options presentation, including validating software costs and checking feasibility for two of the options
  • Drafted closure report

Issues

  • Awaiting some further information from two suppliers where we are checking the feasibility of their software, due to constraints availability it is likely that the project will require an extra week for closure, which has been agreed with the project sponsor

Next Steps

  • Confirm outcome of follow-up actions from solution options, and update analysis report to record this
  • Close project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
18.0 days
Activity this month
1.1 days
Activity this year
18.0 days
Activity to date
17.7 days
Estimate to complete current year
0.3 days
Estimate to complete future years
0.0 days

Project Info

Project
Hope Park Counselling Centre Database Upgrade Requirements
Code
HSS018
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Ben Armstrong
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Start Date
07-Aug-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Feb-2018
Programme Priority
2
Overall Priority
Normal
Category
Discretionary