Report for February 2021

Report Date
February 2021

Achievements this period

  • Project brief  completed
  • Estimation Meetings held
  • Project plan prepared

Issues

  • No issues to report

Next Steps

  • Sign off project brief and plans
  • Apps resources to be requested and secured
  • Business analysis work by LTW staff and Applications
  • System analysis and design to establish direction of project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
2.6 days
Activity this year
2.6 days
Activity to date
2.6 days
Estimate to complete current year
47.4 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.