Status Report for period ending 29 April2022

Report Date
April 2022
  • This project is being suspended 
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
BLUE
RAG Commentary
This Project is being until delivery from Pebblepad is imminent. The programme will monitor progress with supplier on a monthly basis.
Change Status
Has formal escalation taken place?
Yes
Escalated to
Karen Howie
Activity
Approved budget
2.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
1.2 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation