Report for October 2022

Report Date
November 2022

Project going well in terms of cataloguing and promotion.

 

There are problems with the project start and end dates on People and Money. The project dates should be 01 April 2022 to 31 March 2023, but show different dates in both the 'Grants Management' and 'Projects' sections. This has been queried with Jalal Hakimi, but no reply as yet. Moreover, the Project Archivist salary (UE07) is not appearing on People and Money as going out of the grant since it started.

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
There are problems with the project start and end dates on People and Money. The project dates should be 01 April 2022 to 31 March 2023, but show different dates in both the 'Grants Management' and 'Projects' sections of People and Money (presumably incorrect information migrated from Worktribe). This has been queried with Jalal Hakimi, but no reply as yet. Moreover, the Project Archivist salary (UE07) is not appearing on People and Money as going out of the grant since it started.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
Marked 'moderate' on account of issues with People and Money
Activity
Approved budget
220.0 days
Activity this month
18.0 days
Activity this year
128.0 days
Activity to date
128.0 days
Estimate to complete current year
36.0 days
Estimate to complete future years
56.0 days

Project Info

Not available.