Organisation

 

Work/Task Breakdown

Initiate

Prepare brief/plans and submit to WIS

Plan

Review existing TAD; prepare from template if none is available

System Familiarisation: Obtain Code from LIVE; Review System

Impact Analysis: Assess CF9 migration; Assess Mach II capability (draft Migration Strategy Document); Review Impact Analysis; Create Migration Strategy Document (light weight equivalent to SDS)

Build

Establish CF9 environment in DEV

Migrate Code/ Build: Modify code as required to work with CF9; Modify code if appropriate to work with Mach II; Implement Code to DEV; Create Implementation Plan

Peer Test / Code Review

Rework following Peer Test / Code Review

Check

Establish CF9 environment in TEST; Copy code to TEST

Carry out UAT

Rework following UAT

Release

Establish CF9 environment in LIVE; Copy code to LIVE

Make any necessary DB changes or repoints

Initial testing by business area

Go live on migrated application

Close

Prepare closure documentation and submit to WIS

 

Resources Skills and Cost

 

The estimated effort for this project is 40 days. This is a 'large' project from the models created under ITS033 and ITS053. Colleagues in the Development team have now worked on a number of migrations and knowledge and experience of how to do these has increased.

Meeting wth Resource Manager 09/08 in Dev team - resources are currently available and will be assigned once requests are submitted. Similarly, resources are available in Dev Tech and will be assigned to start on their tasks when requests are submitted.