Organisation
Work/Task Breakdown
Initiate
Prepare brief/plans and submit to WIS
Plan
Review existing TAD; prepare from template if none is available
System Familiarisation: Obtain Code from LIVE; Review System
Impact Analysis: Assess CF9 migration; Assess Mach II capability (draft Migration Strategy Document); Review Impact Analysis; Create Migration Strategy Document (light weight equivalent to SDS)
Build
Establish CF9 environment in DEV
Migrate Code/ Build: Modify code as required to work with CF9; Modify code if appropriate to work with Mach II; Implement Code to DEV; Create Implementation Plan
Peer Test / Code Review
Rework following Peer Test / Code Review
Check
Establish CF9 environment in TEST; Copy code to TEST
Carry out UAT
Rework following UAT
Release
Establish CF9 environment in LIVE; Copy code to LIVE
Make any necessary DB changes or repoints
Initial testing by business area
Go live on migrated application
Close
Prepare closure documentation and submit to WIS
Resources Skills and Cost
The estimated effort for this project is 40 days. This is a 'large' project from the models created under ITS033 and ITS053. Colleagues in the Development team have now worked on a number of migrations and knowledge and experience of how to do these has increased.
Meeting wth Resource Manager 09/08 in Dev team - resources are currently available and will be assigned once requests are submitted. Similarly, resources are available in Dev Tech and will be assigned to start on their tasks when requests are submitted.