Report for June 2025

Report Date
June 2025

Achievements This Period

  • new project brief approved - almost done
  • new milestones - done
  • report back on COSIGN issue for DSPACE 6 and plan accordingly - done
  • initial review of UX for Dspace 8 - done
  • complete review and classification and prioritisation of backlog - done
  • Sprints 37 and 38 - done

Issues and Risks

  • COSIGN must be replaced by 30th August

Next Steps

  • new project brief approved
  • new milestones
  • report back on COSIGN issue for DSPACE 6 and plan accordingly
  • review of UX and Design for Dspace 8 
  • Sprints 39 and 40   
  • DataVault Quarterly Release
  •  

Future Milestones

DataVault Quarterly Release 17-Jul-2025
Replace COSIGN with Entra ID for DSpace 6 30-Jul-2025
DataShare : Design Updated 30-Sep-2025
DataShare : Upgrade to DSpace 8 05-Dec-2025
DataShare : Backlog completed 05-Dec-2025
DataVault : Backlog completed 05-Dec-2025
Agile Method : New Ways of Working in Place 05-Dec-2025
Close 19-Dec-2025

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.