Report for August 2017

Report Date
August 2017

Achievements in the last period

  • Rohallion response, feasibility and estimates  to customer requirements received, reviewed.
  • In principle decision to retain Rohallion for development.  
  • Technical preparation for development begun.  

Issues

  • No decision received from customer re the requirement to redevelop the ResearchFish feed.    

Next steps

  • Plan & agreed detailed design and development increments and timescales.
  • Seek stakeholder & WIS approval (if required) for revised milestones arising from this. 
  • Review design products.
  • Begin development.
  • Resolve issue of scope re ResearchFish. 

Milestones

 

Target Datesort descending Previous Date Title Stage Complete  
21-Apr-2017  No date available  Brief sign-off Initiate Yes

 view

09-Jun-2017  21-Apr-2017  Planning sign-off Plan Yes

 view

18-Aug-2017  04-Jul-2017 Discovery end: UX Requirements and back-end analysis defined & signed off Analyse Yes

 view

18-Aug-2017  04-Jul-2017 Back-end design sign-off Analyse Yes

 view

20-Sep-2017  24-Jul-2017 Development Build Sign-off Build No

 view

21-Sep-2017  25-Jul-2017 Install in Test Integrate No

 view

25-Sep-2017  27-Jul-2017 Integration / system test sign-off Integrate No

 view

02-Oct-2017  04-Aug-2017 User Acceptance sign-off Accept No

 view

03-Oct-2017  07-Aug-2017 Deploy to live Deliver No

 view

16-Oct-2017 08-Aug-2017 Deployment / handover to support sign-off Deliver No

 view

16-Oct-2017  22-Aug-2017 Post-implementation support sign-off Deliver No

 view

27-Oct-2017  29-Aug-207 Project Closure Close No

 view

   
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
AMBER
Overall
GREEN
RAG Commentary
Scope - Status of ResearchFish feed redevelopment to be agreed after 3rd party web design delivered. (Expected w/c 25th Sept). No SMT action required.
Change Status
Activity
Approved budget
154.0 days
Activity this month
4.9 days
Activity this year
4.9 days
Activity to date
36.6 days
Estimate to complete current year
52.3 days
Estimate to complete future years
0.0 days