Report for August 2017
- Report Date
- August 2017
Achievements in the last period
- Rohallion response, feasibility and estimates to customer requirements received, reviewed.
- In principle decision to retain Rohallion for development.
- Technical preparation for development begun.
Issues
-
No decision received from customer re the requirement to redevelop the ResearchFish feed.
Next steps
- Plan & agreed detailed design and development increments and timescales.
- Seek stakeholder & WIS approval (if required) for revised milestones arising from this.
- Review design products.
- Begin development.
- Resolve issue of scope re ResearchFish.
Milestones
| Target Date |
Previous Date | Title | Stage | Complete | |
|---|---|---|---|---|---|
| 21-Apr-2017 | No date available | Brief sign-off | Initiate | Yes | |
| 09-Jun-2017 | 21-Apr-2017 | Planning sign-off | Plan | Yes | |
| 18-Aug-2017 | 04-Jul-2017 | Discovery end: UX Requirements and back-end analysis defined & signed off | Analyse | Yes | |
| 18-Aug-2017 | 04-Jul-2017 | Back-end design sign-off | Analyse | Yes | |
| 20-Sep-2017 | 24-Jul-2017 | Development Build Sign-off | Build | No | |
| 21-Sep-2017 | 25-Jul-2017 | Install in Test | Integrate | No | |
| 25-Sep-2017 | 27-Jul-2017 | Integration / system test sign-off | Integrate | No | |
| 02-Oct-2017 | 04-Aug-2017 | User Acceptance sign-off | Accept | No | |
| 03-Oct-2017 | 07-Aug-2017 | Deploy to live | Deliver | No | |
| 16-Oct-2017 | 08-Aug-2017 | Deployment / handover to support sign-off | Deliver | No | |
| 16-Oct-2017 | 22-Aug-2017 | Post-implementation support sign-off | Deliver | No | |
| 27-Oct-2017 | 29-Aug-207 | Project Closure | Close | No |
- Approved budget
- 154.0 days
- Activity this month
- 4.9 days
- Activity this year
- 4.9 days
- Activity to date
- 36.6 days
- Estimate to complete current year
- 52.3 days
- Estimate to complete future years
- 0.0 days