Report for August 2017
- Report Date
- August 2017
- Achievements this period:
- Phased approach for full service delivery agreed to support key functionality going live asap.
- Encryption approach agreed.
- Edina engaged re provision of coding resources.
- Issues
- Delay with coding work – We are several weeks behind the re-plan put together in June. Edina are lined up to provide resources once we have completed the function and technical reqs.
-
Delay with provision of tape infrastructure in DCs (being delivered by the Backup Infrastructure Project). We have a target date of end of Sept. for this now. Coding contractor has not worked out as hoped and has now left the Uni with little progress made.
-
Delay with provision of the cloud service. Target date of end of Sept. for this now.
- Risks - Full Service Solution:
-
No confirmed resource to document\design how encryption and key management will be applied, and potentially to deploy this as well. It is un-clear how much effort this will take, and what impact it will have on the time-line.
-
Change in PM – Steve Taylor’s IoT programme needs more of his time and he needs to step back from the DataVault project. Maurice Franceschi is working with Apps team to identify a new PM.
-
Kenton D’Mellow has been assigned to a key new project which may impact his availability for DataVault.
- The policy for the Interim Service is that no personal data should be stored on the system. We are relying on depositors adhering to this policy, but there is a Risk that personal data may make it on to the system.
- Next Steps
- Confirm resource for encryption design (and implementation?) work.
- Completed functional and technical requirement docs.
- Document functionality questions that the project team need the Board to advise on, and present these to the Board for feedback.
-
Re-planning and confirm new expected go-live date for phase 1 of the full service solution.
-
Note re budgets: This project has a mix of capital and revenue budgets, and core funding on this project. The revenue budget is a fixed cost for RSS effort and the other teams are core funded, so there is not effort tracking against budget on this project.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days
