Report for August 2017

Report Date
August 2017
  • Achievements this period:
    • Phased approach for full service delivery agreed to support key functionality going live asap.
    • Encryption approach agreed.
    • Edina engaged re provision of coding resources.  
  • Issues
    • Delay with coding work – We are several weeks behind the re-plan put together in June.   Edina are lined up to provide resources once we have completed the function and technical reqs.
    • Delay with provision of tape infrastructure in DCs (being delivered by the Backup Infrastructure Project).  We have a target date of end of Sept. for this now. Coding contractor has not worked out as hoped and has now left the Uni with little progress made.

    • Delay with provision of the cloud service. Target date of end of Sept. for this now.  

  • Risks - Full Service Solution:
    • No confirmed resource to document\design how encryption and key management will be applied, and potentially to deploy this as well.   It is un-clear how much effort this will take, and what impact it will have on the time-line.

    • Change in PM – Steve Taylor’s IoT programme needs more of his time and he needs to step back from the DataVault project.  Maurice Franceschi is working with Apps team to identify a new PM.

    • Kenton D’Mellow has been assigned to a key new project which may impact his availability for DataVault.

    • The policy for the Interim Service is that no personal data should be stored on the system.  We are relying on depositors adhering to this policy, but there is a Risk that personal data may make it on to the system.  
    • Next Steps
      • Confirm resource for encryption design (and implementation?) work.
      • Completed functional and technical requirement docs.
      • Document functionality questions that the project team need the Board to advise on, and present these to the Board for feedback.
      • Re-planning and confirm new expected go-live date for phase 1 of the full service solution.

 

Note re budgets:   This project has a mix of capital and revenue budgets, and core funding on this project.  The revenue budget is a fixed cost for RSS effort and the other teams are core funded, so there is not effort tracking against budget on this project.

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
RED
RAG Commentary
Change - Project has returned to green following re-planning with new go-live target dates (based on a number of assumptions).
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.