Report for September 2017

Report Date
September 2017

Achievements in the last period

  • Design products delivered and reviewed. 
  • Rohallion Ltd engagement agreed in principle and resource availability confirmed. 
  • ResearchFish and Thompson/Reuters feeds confirmed as out of scope of development.  
  • Faceted search confirmed as out of scope for Increment 1.
  • Technical preparation for development completed.
  • Customer confirmed IS should support delivered website.
  • Customer confirmed that ERI will take on support of SQL Server & Access components, not IS. 
  • Delivery timescales of 15/11/17 (Increment 1) agreed with stakeholders and authorised by WIS. 
  • Second delivery increment Jan 2018 - March 2018 agreed with stakeholders and authorised by WIS.   

Issues

  • None.      

Next steps

  • Finalise Rohallion contractual engagement.
  • Begin development. 
  • First-cut review of pages  of website w/c 30/10/17. 
  • Agree Drupal application support responsibilities. 

Milestones

 

Target Datesort descending Previous Date Title Stage Complete  
21-Apr-2017  No date available  Brief sign-off Initiate Yes

 view

09-Jun-2017  21-Apr-2017  Planning sign-off Plan Yes

 view

18-Aug-2017  04-Jul-2017 Discovery end: UX Requirements and back-end analysis defined & signed off Analyse Yes

 view

18-Aug-2017  04-Jul-2017 Back-end design sign-off Analyse Yes

 view

10-Nov-2017  24-Jul-2017 Development Build Sign-off Build No

 view

13-Nov-2017  25-Jul-2017 Install in Test Integrate No

 view

14-Nov-2017  27-Jul-2017 Integration / system test sign-off Integrate No

 view

22-Nov-2017  04-Aug-2017 User Acceptance sign-off Accept No

 view

22-Nov-2017       07-Aug-2017 Deploy to live Deliver No

 view

22-Nov-2017 08-Aug-2017 Deployment / handover to support sign-off Deliver No

 view

22-Nov-2017  22-Aug-2017 Post-implementation support sign-off Deliver No

 view

30-Mar-2018  29-Aug-207 Project Closure Close No

 view

   
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
154.0 days
Activity this month
5.7 days
Activity this year
10.6 days
Activity to date
42.3 days
Estimate to complete current year
89.8 days
Estimate to complete future years
0.0 days