Report for February 2018

Report Date
February 2018

Achievements in Last Period

  • Development progressed
  • Closure of issue re Staff email data
  • Training completed
  • Go Cab submission drafted

Issues

  • Special CAB - Potential Delay to Go Live - A submission was made to the Special CAB to progress to Go Live on 13th March.  It has been proposed this is extended out further to 22nd March.  See issue 5
  • Telephone and Student email data - Resolution of how this data will be gathered has been been challenging.  Two solutions are now being reviewed however the data will not be available for Go Live. See issue 6 and 7

Next Steps 

  • UAT complete
  • Pre Live Communications
  • Sign Off / Approval
  • Go Live
Project Status
RAG Status
Time
RED
Cost
AMBER
Scope
RED
Overall
RED
RAG Commentary
Issue: RED: As outlined in January a lengthier than expected period to resolve how emails and telephone numbers will be gathered impacted the resource and timeline for this project. This has been further impacted by Industrial Action and Weather events leading to an escalation of Time and Cost status. Additional scope now required to progress email and phone data has also increased impact to required resources.
Change Status
Activity
Approved budget
145.0 days
Activity this month
26.4 days
Activity this year
113.5 days
Activity to date
113.5 days
Estimate to complete current year
35.7 days
Estimate to complete future years
0.0 days

Project Info