Report for February 2018

Report Date
February 2018
Achievements in Last Period
  • UI builds, deposit and retrieval including secondary storage (TSM) and encryption work completed (Sprint 8)
  • UI  updates, Pure API review, test server TSM client, 'chunking' tests, cloud API review and cloud requirements in progress (Sprint 9)
  • Agreement with ENT Unix Systems team to support key management
Risks/Issues
  • Delay in selecting a cloud storage service provider could impact third storage development and test dates
  • Loss of Pure expert could impact that area of work
  • Some team members impacted by industrial action; Sprint 9 extended for 2 weeks to 4 weeks
  • Delay in GDPR initial assessment
Next Steps
  • Start integration development on UI/Broker/Pure
  • Run G-Cloud 9 framework search for suitable cloud backup suppliers
  • Finalise UI help text and policy content
  • Cloud storage API development
  • Review and complete GDPR initial assessment

Milestones

Target Date
Title
Stage
Complete
11-Oct-2017 Full service solution initial planning complete Plan yes

16-Oct-2017

Scrum approach adopted; first sprint started; project tasks added to Jira

Plan Yes
02-Feb-2018 Website wireframes approved Design Yes
28-Feb-2018 Deposit/retrieval/encryption (TSM) completed Build Yes
06-Mar-2018 Website UI screens completed Build No
21-Mar-2018 Deposit/retrieval/encryption (Cloud) completed Build No
26-Mar-2018 Demonstration of deposit archiving and retrieval to internal (TSM) and  external cloud storage Deliver No
30-Mar-2018 GDPR review completed Analyse No
30-Mar-2018 Full test server operational Build No
13-Apr-2018 Integration testing completed Integrate No

17-Apr-2018

Minimal viable product (MVP) for Data Vault available for use Deliver No
24-Apr-2018 User training completed Deliver No
15-May-2018 UAT completed Accept No
15-May-2018 Data Vault GDPR compliant Deliver No
22-May-2018 Production environment availabe Deliver No

25-May-2018

Data Vault released

Deliver No
TBA Data Vault launched Deliver No
22-Jun-2018 Project closure approved Close No
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
468.0 days
Activity this month
37.0 days
Activity this year
193.0 days
Activity to date
193.0 days
Estimate to complete current year
223.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.