Report for March 2018

Report Date
March 2018

 

Achievements this month

  • Project initiated
  • Started to add content to the Projects Website

Issues

  • None

Next Steps

  • Continue to set up Projects Website
  • Complete project planning by end of April
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.