Report for June 2018

Report Date
June 2018

Achievements this month

  • First batch of changes made and tested.
  • Release slots booked.

Issues

  • Original budget insufficient to deliver all of the scope.  Budget increase approved and project re-planned accordingly.

Next Steps

  • Continue working through the established backlog and releasing to a fortnightly schedule, as per other SSP projects.
Project Status
RAG Status
Time
RED
Cost
RED
Scope
GREEN
Overall
RED
RAG Commentary
Budget increase and new closure milestone to be approved. No SMT action required
Change Status
Activity
Approved budget
50.0 days
Activity this month
19.0 days
Activity this year
28.0 days
Activity to date
28.0 days
Estimate to complete current year
40.0 days
Estimate to complete future years
34.0 days