Report for July 2018

Report Date
July 2018
Achievements in Last Period
  • UAT testers identified and familiarisation sessions held

  • Oracle cloud archive storage service in place

  • TSM licences purchased and install after insufficient available in pool

  • New test (demo) environment in place apart from KeyStore key management

  • Draft GDPR DPIA completed and reviewed by DPO

  • Plan revised in line with delay to UAT start

Risks/Issues
  • UAT delayed by 4 weeks by issues with Oracle service completion, TSM licences unavailable and HashiCorp integration
  • HashiCorp Vault dropped as key management service
  • Soft launch may be delayed due to clash with ISG change freeze in September
Next Steps
  • Complete live environment build
  • Run UAT to start week 06/08/2018
  • Run full end-to-end performance test (start 20/08/2018)
  • Run Schools workshops for potential DV users in August 
  • Update GDPR DPIA with mitigation and residual risks
  • Complete Service Level Definition (SLD)
  • Deliver DV soft launch on 03/09/2018

Milestones

Target Date
Title
Stage
Complete
11-Oct-2017 Full service solution initial planning complete Plan Yes

16-Oct-2017

Scrum approach adopted; first sprint started; project tasks added to Jira

Plan Yes
02-Feb-2018 Website wireframes approved Design Yes
28-Feb-2018 Deposit/retrieval/encryption (TSM) completed Build Yes
06-Mar-2018 Website UI screens completed Build Yes
30-Mar-2018 GDPR review  in progress Analyse Yes
13-Apr-2018 Deposit/retrieval/encryption (Cloud) completed Build Yes
20-Apr-2018 Full test server operational Build Yes
23-Apr-2018 Demonstration of deposit archiving and retrieval to internal (TSM) and  external cloud storage Deliver Yes
25-May-2018 Integration testing completed Integrate Yes
25-May-2018 Minimal viable product (MVP) for Data Vault available (interim UI) Deliver Yes
31-Jul-2018 Cloud service contract in place Integrate Yes
03-Aug-2018 HashiCorp key management in place for test environment Integrate No
03-Aug-2018 Full test environment in place Integrate No
06-Aug-2018 UAT start Accept No
13-Aug-2018 Production environment available for performance testing Deliver No
17-Aug-2018 UAT completed Accept No
17-Aug-2018 Data Vault GDPR compliant Deliver No
10-Sep-2018 Data Vault soft launch Deliver No
26-Oct-2018 End of early adoption period Deliver No
05-Nov-2018 l DV service operational Deliver No
23-Nov-2018 Project closure approved Close No
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Issue - Delay to UAT start caused by late provision of Oracle cloud service, need to buy additional TSM licences and issues with HashiCorp key management integration.
Change Status
Activity
Approved budget
468.0 days
Activity this month
52.0 days
Activity this year
320.5 days
Activity to date
320.5 days
Estimate to complete current year
0.0 days
Estimate to complete future years
40.0 days