Report for July 2018

Report Date
July 2018

Achievements in Last Period

  • Go live of changes including cookies banner / GDPR alignment

Issues

Milestones have slipped due to issues outlined in JIRAS however previously revised milestones are on track to be met.

Next Steps 

  • API development and Go Live
  • Project Closure
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
AMBER: Issue: The issue aligned to quality of telephony data and the problems encountered linked to undertaking daily crawls has impeded the ability to close this project. These issues have been escalated to Project Sponsor / Programme Manager and on-going work is being progressed via JIRAs. The project has been re-planned to now close in August and this will be monitored closely and escalated as required by Project Manager.
Change Status
Activity
Approved budget
185.0 days
Activity this month
4.7 days
Activity this year
189.0 days
Activity to date
189.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
5.0 days