- Report Date
- September 2018
Achievements in Last Period
Review and re-alignment of resource / budget aligned to slippage.
Issues
Milestones have slipped due to issues outlined in JIRAS and impact of resource availability to resolve.
Next StepsĀ
- PICCL submitted / approved to agree new milestones / budget to reach closure
- API development and Go Live for student email
- Project Closure
- Approved budget
- 185.0 days
- Activity this month
- 2.6 days
- Activity this year
- 4.2 days
- Activity to date
- 195.0 days
- Estimate to complete current year
- 19.5 days
- Estimate to complete future years
- 0.0 days