Report Date
October 2018
Achievements in Last Period
Progress of final "Must Have" jiras including:
API development and Go Live for student email
Best Bets
Improved Results
Issues
Milestones have slipped due to issues outlined in JIRAs and impact of previous resource availability to resolve. Remedial actions have been put in place and go live is expected in early December.
Next Steps
Final Release to "Live"
Close
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
AMBER: The issue aligned to quality of student emails API and the problems encountered linked to undertaking daily crawls is currently being addressed and closure is now expected before the end of the year. The impact to the current live service and users is minimal however final milestone delivery timescales / cost have been impacted.
Change Status
Time
Significant
Cost
Moderate
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
Yes
Escalated to
These issues have been escalated to Project Sponsor, Programme Manager, and Portfolio Manager and on-going work is being progressed via JIRAs.
Change Commentary
Moderate: There is contingency actions in place and the impact to the current live service and users is minimal. The project has been re-planned to now close by the end of 2018.
Activity
Approved budget
185.0 days
Activity this month
0.0 days
Activity this year
1.6 days
Activity to date
192.7 days
Estimate to complete current year
17.0 days
Estimate to complete future years
0.0 days