Report for January 2019

Report Date
January 2019

Achievements in Last Period

  • Completion of "Must Have" jiras
  • Agreement on BAU jiras
  • Draft Closure Report

Issues

  • Budget resolution required at programme level.  The additional 15 days funding required to complete this project has been escalated to Programme Level.

Next Steps 

  • Closure
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
AMBER: The issue aligned to quality of student emails API and the problems encountered linked to undertaking daily crawls has now been addressed however the milestone delivery timescales and overall cost were impacted.
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
Yes
Escalated to
These issues have been escalated to Project Sponsor, Programme Manager, and Portfolio Manager previously.
Activity
Approved budget
185.0 days
Activity this month
0.4 days
Activity this year
12.5 days
Activity to date
203.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.