Report for March 2019

Report Date
March 2019

Achievements

  • Sponsor confirmed on December 21 that all projects should be closed in January
  • Close documents prepared, awaiting confirmation that project can be closed - meeting with sponsor scheduled for April 11, 2019

Issues

  • N/A

Next steps

  • Close project

Milestones

  • N/A

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
GREEN
RAG Commentary
All work has stopped, awaiting closure of the project
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
34.0 days
Activity this month
0.0 days
Activity this year
8.2 days
Activity to date
28.1 days
Estimate to complete current year
19.6 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.