June 2019

Report Date
June 2019

Achievements this period

  • All PCs for all campus sites have now been delivered

Next Steps

  • Campus teams to install any remaining presenter PCs during the upcoming teaching spaces upgrades.

 

Closing project due to all PCs being delivered and installations being scheduled for completion.  Closure report.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.