Report for June 2023

Report Date
June 2023

During June,

The main highlight was to determine the preferred bidder for the new Inspections and Inventory application.

With regards to the active projects,  one is reporting Green, one Amber and one Red.

The Hotel Management system project has been formally withdrawn.

Billing for Q1 - Q3 has been processed 

Forward Look 

Resource Summary 

 

 

Section Two: Projects Not Started

 

Project Info Programme Managers Commentary RAG Status 
AP23-030 Nursery Management System  After discussions with the the project sponsor, the decision has been taken to re-schedule the project start date to September 2023.     Green

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ACS043

Delivered Catering Implementation 

Category: Discretionary

Sponsor Funded 

Milestones

Milestone Due Date
People and Money Integration UAT 30-Jun-2023
People and Money Integration - Live 17-Jul-2023
People and Money Integration DSOR 28-Jul-2023
Closure 11-Aug-2023

 

RAG Status: RED 

Report by Andy Stewart for June 2003 

Achievements This Period

Phase 2 - Integration with People and Money

  • Initial connectivity tests continued with additional bookings in which 
    • booking process appeared to complete with order details registered on the supplier system , although no requisition details returned to People and Money

Issues

  • Customer notification of order is being issued in advance of requisition / purchase order process and this has been noted by the supplier 
    • Whilst the test order appeared to complete successfully, there did appear to be any related requisition details created within People and Money and the supplier was  seeking clarification regarding the specific endpoint in which the data is being posted  
    • The supplier has advised that after further investigation, the method of communication(punchout) between the  application and People and Money may require to be changed and this is now being further investigated
  • Current project delivery milestone of 14th July will not be met and there will be the requirement to carry over the project to 2023-2024

Next Steps

  • Re-plan the project
  • Determine reason for missing requisition details 
  • Supplier to amend workflow process with regards order confirmation 
  • Continue order process testing 
  • Commence User Acceptance Testing once the full order processing has been fully completed

RAG Commentary

Issue: The punchout process between Spoonfed and P&M has still to be successfully completed. The supplier has advised that after a further technical re-evaluation, additional code changes will be required to be incorporated into the punchout, but have not specified a delivery date. Impact: There will now be the requirement to carry over the project into 2023-2024 whilst the ACE catering team continue to have the large and unsustainable administrative burden to manually raise journals to re-charge internal customers. Next Steps: Maintain contact with the supplier regarding potential delivery dates whilst keep both ACE and People and Money personnel informed.

ACS044

Inspections and Inventory

Category: Discretionary 

Sponsor Funded 

Milestones

Milestone Due Date
Confirm Preferred Supplier 23-Jun-2023
Contract Award 07-Jul-2023
Close 21-Jul-2023

 

RAG Status: GREEN

Report by Andy Stewart for June 2023

Link to Project Report 

ACS045                                               Student Accommodation System 

Sponsor Funded 

Milestones:

Milestone Due Date
Planning 14th-July 2023
Analysis  15th-July-2023
Direct Award Report Completed 31st-July-2023

Legal to review and signoff contract

15th-Nov-2023

Award Contract

30th-Jun-2023

Signoff Contract

22-Nov-2023

Close

7th-Dec-2023

 

RAG Status: AMBER

Report by Colin O'Sullivan for June 2023

Link to Project Report 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

 

Section Five: Programme Risk and Issue Log 

Risk Reference Description Risk Owner Risk Status  Last Reviewed Date 
12

ACE Systems Integrations with People and Money

Andrew Glass Amber  10/07/23
13

Lack of resources required to deliver the programme 

Andrew Stewart Amber 10/07/23
14

Insufficient budget to deliver 2022/2023 programme of work

Andrew Glass Closed (was Green)  10/07/23
15

Delivery of the scheduled programme of work

Andrew Glass Closed (was Amber) 10/07/23
16 Lack of ACE resources required to deliver the programme Andrew Glass Amber 10/07/23
17 Impact of potential industrial action Andrew Glass Green  10/07/23
18  Unavailability of People and Money Resource  Martyn Peggie Amber  10/07/23
Issue Reference Description Issue Owner Last Reviewed Date
49 Delivered Catering Integration with People and Money  Ian Macaulay  10/07/23

Section Six : Programme Meeting Minutes

The minutes from the programme meetings since July 2018 can be located on the Accommodation Catering and Events SharePoint site

 

AttachmentSize
Image icon 202306_rag.png210.33 KB
Image icon 202306_resources.png52.16 KB
Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No
RAG Commentary
Issue: Both technical and resource challenges exist in the delivery of the current active projects with regards to a) Delivered Catering Implementation as the newly developed punch-out has still to be integrate; b) Inspections and Inventory timeline is extremely tight to complete the procurement and implement a new solution prior to the next summer student intake. Impact: Existing business solutions, whilst not ideal will enable business as usual to continue. Next Steps: Respective project teams to focus on working with the related suppliers to deliver the projects within the current timeframes.