Report for March 2024

Report Date
March 2024

During March,

  • The main focus of activity has focused on the business case. As part of this activity, the work to estimate the kx migration has been completed 
  • Further discussions regarding the Delivered Catering integration have directed that the project suspension be extended to the end of July 

There will be no new projects submitted for 2024-2025. The only project activity scheduled for next year is 

  • ACS045 - Continuation of Student Accommodation System procurement 
  • Migration of on-premise Kx environment to the supplier hosted environment

 

Forward Look 

Resource Summary 

 

 

Section Two: Projects Not Started

 

Project Info Programme Managers Commentary RAG Status 
   No projects to commence  Green

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ACS043

Delivered Catering Implementation 

Category: Discretionary

Sponsor Funded 

Milestones

Revised milestones to be confirmed

Milestone Due Date
People and Money Integration UAT t.b.c.
People and Money Integration - Live t.b.c.
People and Money Integration DSOR t.b.c.
Closure t.b.c.

 

RAG Status: SUSPENDED 

Report by Andy Stewart for March 2024

Link to report for March 2024

ACS045                                               Student Accommodation System 

Sponsor Funded 

Milestones:

Milestone Due Date
Direct Award Report Completed 1st September 2024

Legal to review and signoff contract

22nd September 2024

Award Contract

23rd September 2024

Signoff Contract

30th September 2024

Close

16th October 2024

 

RAG Status: AMBER

Report by Colin O'Sullivan for March 2024

 

Link to Project Report

Report for March 2024 | Project Management (ed.ac.uk)

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary
ACS044 - Inspection and Inventory 

Project Closure Report 

Project Closure Noted 

 

Section Five: Programme Risk and Issue Log 

Risk Reference Description Risk Owner Risk Status  Last Reviewed Date 
13

Lack of technical resources required to deliver the programme 

Andrew Stewart Green  08/04/24
20 Programme Delivery 2023-2024 Andrew Stewart  Green (was Amber ) 08/04/24
Issue Reference Description Issue Owner Last Reviewed Date
49 Delivered Catering Integration with People and Money  Ian Macaulay  08/04/24

Section Six : Programme Meeting Minutes

The minutes from the programme meetings since July 2018 can be located on the Accommodation Catering and Events SharePoint site

 

AttachmentSize
Image icon 2024-03_rag.png83.19 KB
Image icon 2024-03_resources.png41.35 KB
Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No
RAG Commentary
Issue: There is currently uncertainty regarding the delivery of the suspended project ACS043 Delivered Catering Implementation whilst further clarity is sought regarding the internal re-charging process. Impact: The programme will not deliver the planned activity within 2023-2024 and this could impact on planned sponsor funded revenue. Next Steps: Review the project status with the project sponsor in early December 2023.