Report for October 2013
- Report Date
- October 2013
Report compiled by Adam Wadee, IS Apps Programme Manager for Stuart McFarlane (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section Five: New Approved Projects from 13/14 Annual Plan
Section One: Programme Commentary, RAG and Resources Update
Overall the programme is in reasonable shape but the pressure on staff to deliver several high priority projects in quick succession is considerable. There is also a high degree of change to be experienced by end users and supported by IS.
Good progress has been made with the Wiki upgrade project (WEB004) which is on schedule to deliver the new live service in December. Live migrations are in progress under the BOXI Upgrade and will continue through November and December, however the remaining estimates indicate that additonal effort will be required to complete the project. The Office 365 Migration for staff (COM008) project has needed a lot of R&D in order to define the scope, but it is now taking shape and aims to start migrations from November.
The programme is currently running over budget due to additonal effort for essential work on the BOXI Upgrade project, and COM007. However, with the Discussion Forum Upgrade project unlikely to be needed, we will use the days to bring the budget in line.
Overall Programme RAG: AMBER
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
AP34-035 EVES Voting Application Upgrade | Plan To start Q1 2014. Dependencies
|
AP34-036 Document Management System (Serengeti) Upgrade | Plan Currently planned to start Sep 2013. With current programme schedule of projects, this does not look possible. Dependencies |
AP34-037 Coldfusion 9 Upgrade for VRS | Plan To start Q1 2014. Dependencies |
AP34-047 Discussion Forums Upgrade | Plan Project not expected to be required, and will therefore be withdrawn. Dependencies |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
ITS092 AP12-010 BOXI Upgrade
Category: Compliance Milestones
AMBER
| Report by Craig Middlemass for October 2013 Achievements in Last Period
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
COM001 Office 365 for Students
Category:Discretionary Milestones *To be replanned*
RAG Status AMBER |
Report by Tim Gray for October 2013 Achievements in Last Period
Next Steps
Project changed to AMBER as progress has been made on issues but milestones not yet re-planned
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
COM007 AP23-001 Migrate IDM to Oracle SOA Suite 11g and Upgrade Grouper Compliance Milestones - to be replanned
RAG Status RED
| Report by Stevie Conlon for October 201 Achievements in Last Period
Issues
The project is Red as dates for Phase 1,2,3 will be replanned to accomodate annual leave, and revised Phase 2 requirements and the inclusion of new work transferred from COM008. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
COM008 Migrate Exchange to Office 365 Discretionary
Milestones
RAG Status AMBER | Report by Morna Findlay for October 2013 Achievements this period
End of planning achieved. Diary sharing issues for two pilot test users resolved. Cross-site diary sharing issues further investigated. Further testing of mail and calendar migrations, including performance evaluations. Initial design for .NET provisioning scripts delivered. Draft requirements for provisioner delivered.
Outstanding IssuesProvisioning requirements to be signed off. Provisioner design to be signed off. Diary-sharing investigations to be completed. Exchange user migration scripts to be signed off. Exchange user migration performance issues to be completed. Migration timetable to be agreed. Business requirements to be agreed.
Next Steps
Migration process for staffmail users to be developed. Test infrastructure to be completed with assistance of external contractor. Design of exchange and powershell provisioner scripts. Migration date to be agreed.
The project is AMBER as issues with diary-sharing and performance mean that the migration timetable has not yet been agreed. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
WEB003 Mobile Information Solution With MyEd - Phase 1Compliance
Milestones
RAG Status AMBER | Report by Maurice Franceschi for October 2013 The project tasks up to the end of November have been planned and people assigned to the tasks. All tasks required have been requested in ASTA, showing a delivery date the week before Easter 2014. New milestones and estimates will be set once resourcing of Priority 1 projects is completed, the build of the Prototype and all development on it are completed - early December. A full list of the taks to be planned and requested/assgined effort are shown in the tasklist. Project now set at 301 days, with 130 days estimated for the Phase II, which wil be a new project. The project is 24 days over estimate - no need to act on this as yet. Work remains on schedule. Due to the current budget overrun and because some additional effort is needed, and also that the milestones could be rejected by WIS, the project is at Amber.
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
WEB004 WIki Upgrade Compliance
The project RAG status is GREEN
| Report by Morna Findlay for October 2013Achievements this Period
Upgrade of TEST completed Integration review approved. Plugin work agreed with supplier (Adaptivist) and plugins applied and tested Further communications sent to wiki user group and wiki space owners New milestones agreed and upgrade date set. User acceptance testing begun.
Outstanding Issues
Various JIRA issues reported as a result of UAT. Solutions to be found for user groups for whom 2 December upgrade date is an issue ( Genomics and Education) Decision on whether to implement improved resilience measures to be taken.
Next Steps
Meet with wiki user group to approve TEST Sign off user acceptance testing Load testing to be carried out. read-only wiki to be tested Deployment plan to be agreed.
The project status is GREEN | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
CMW009 Video & Media Strategic Review Discretionary
The project RAG status is GREEN | Report by Karen Stirling for October 2013Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Project Code (AP Number) Project Title
Discretionary/Compliance/Funded | Report by [PM] This project was closed/withdrawn on dd-mmm-yy [for closures] Please see the Completion Report / Closure Review for further information [include link]. [for withdrawn] Please see the PRICCL log for further details [include link].
|
COM006 (AP23-034) CSE Reporting and Business Intelligence Optimisation Discretionary | Report by Karen Stirling This project was closed on 23-Sep-13 Please see the Completion Report for further information |
WEB002 ECA CMS TechnologyFunded | Report by Arthur Wilson ECA have confirmed that they cannot commit to the second phase of the WEB002 project. The second phase was originally planned to implement cosign and ldap integration for the new ECA drupal website. As a result, the project will be withdrawn from the 13/1/4 CMW programme. Note that the phase 1 delivery of the basic drupal website for ECA will continue as a Service Management (RDS) task. |
Section Five: New Approved Projects from 13/14 Annual Plan
Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.
Project Info | Project Managers Commentary |
Planning - Delivery - RAG Status | Plan
Dependencies |