Report for June 2014

Report Date
June 2014
 

Report compiled by Adam Wadee, IS Apps Programme Manager for Stuart McFarlane  (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section Five: New Approved Projects from 14/15 Annual Plan

 

Section One: Programme Commentary, RAG and Resources Update

Look-ahead to the end of the 13/14 financial year:

  • Projects planned to close before year end:
    • WEB003
  • Unplanned Carry over:
    • ITS092 (Agreeing a date to move BI Explorer move to 2nd virtual machine delaying project)
    • COM008 (Final decomisioning and Test infrastructure set-up to be completed)
    • CMW010
    • CMW012 (resource conflicts have delayed progress)
  • Planned Carry over:
    • WEB005
    • COM007
    • COM011

 

This programme is overall RED for the current year as some projects have had to be re-planned and are now expected to complete in 14/15. The reason the programme is RED is that the work will not be completed in this year, and therefore there is unplanned carry-over. The Programme Manager and Programme Owner have an action to agree how to address this next year, as there is no allowance for this in the current list of planned projects.

Overall Programme RAG: RED

 

 

 

 Section Two: Projects Not Started

 

 

Project InfoProject Manager's Commentary
Wiki Service Improvement

Project to start December 2014

No dependencies.

Committee Intranet Migration

Project to start October 2014

No dependencies.

SharePoint Demonstrator Projects

Project to start October 2014

No dependencies.

BI Additional Tools –Dashboards/ReportWriter

Project to start August 2014

Dependant on ITS092 completing.

Update and Rationalise Windows Web Hosting

Project to start August 2014

Will have impact on MVM002.

MyEd Continuous Improvement

Project to start September 2015

MyEd Enhanced Mobile Interface

Project to start February 2015

Dependant on WEB005 completing.

Notifications Backbone [Year 1]

Project to start November 2014

No dependencies.

 

Section Three: Projects in Progress

 

Project InfoProject Manager's Commentary

ITS092  AP12-010

BOXI Upgrade

 

Category: Compliance

Milestones

 

Target DateMilestone
11-Jul-2014Deployment Sign Off Review
30-Jul-2014Close Project
   RAG Status
Amber

 

Report by Craig Middlemas for June 2014

Achievements in Last Period
  • None
Issues
  • Finding an appropriate date for an outage to move BI Explorer to a 2nd virtual machine has been problematic, trying to avoid critical points in the academic year.
  • The project will be extended into 14/15 to allow for the BI Explorer move to be undertaken as part of the project, funding and approval need to be sought.
Next Steps
  • Secure funding and approval to extend into 2014/15
  • Deploy fix for UNX Universes to live and deploy Audit universe
  • Move BI Explorer onto a 2nd machine on Live
  • Close the project
 

 

 

 

 

 

 

 

 

 

 

COM007 AP23-001

Migrate IDM to Oracle SOA Suite 11g and Upgrade Grouper

Compliance

Milestones - Proposed, Placeholder and TBC

09-Jul-14

Phase 2 Inbound - ASOR

16-Jul-14

Phase 2 Inbound - Deploy

24-Jul-14

Phase 2 Inbound - DSOR/Closure (proposed)

11-Jul-14

Phase 3A Pull Services & Grouper Upgrade - Initiate (placeholder)

24-Jul-14

Phase 3A Pull Services  - Design Sign Off (placeholder)

25-Jul-14Phase 3A Grouper Upgrade - Design Sign Off (placeholder)

05-Sep-14

Phase 3A Pull Services & Grouper Upgrade - Build Sign Off (placeholder)

10-Oct-14

Phase 3A Pull Services & Grouper Upgrade - ASOR (placeholder)

24-Oct-14

Phase 3A Pull Services & Grouper Upgrade - Deploy (placeholder)

07-Nov-14

Phase 3A Pull Services & Grouper Upgrade - DSOR/Closure (placeholder)

TBC

Database Migration - Initiate

TBC

Database Migration - Design Sign Off

TBC

Database  - Build Sign Off

TBC

Phase 4 Grouper - ASOR

TBC

Phase 4 Grouper - Deploy

TBC

Phase 4 Grouper - DSOR/Closure

TBC

COM007 - Project Closure

 

RAG Status

GREEN

Report by Karen Stirling for June 2014

Achievements in Last Period

  • Phase 2 UAT commenced on 2nd June
  • Phase 2 Inbound Implementation / rollout plan review and updated
  • Phase 2 Change Control and Service Alerts have been set up with communications being issued out by Service Management
  • Phase 2 Load Testing completed and raised no cause for concern
  • Phase 3A resource requests for early design to commence in July.
  • Phase 3A placeholder dates approved by WIS with old Phase 3 and 4 withdrawn
              

Issues

  • Review of Grouper requirements have highlighted the infrastructure this should be deployed to, is on new VM, effort to be assessed by Dev Tech resource in discussion with Tech Management
  • Due to a delay to deploy Phase 2 to IDM test and availability of developer resource during UAT the project team have reviewed ASOR, Deploy and DSOR milestone dates for Phase 2 and new dates have been agreed. The project requires to be implemented by the latest date of w/c 14th July so as not to impact lead up to year end change freeze dates on IDM. Our deployment coincides with ITS103 deployment over same period. There have been a number of discussions to ensure both projects are not at risk from each other activities. Also Essential Core Maintenance taking place prior to these deployments on 15th July. Production Management have put in place a number of checks to ensure environments are back in place before any of our activity begins on 16th July.
  • Database Migration dates to be agreed on review of remaining budget.
  • Phase 3A BRD has been issued out for review/approval no new requirements have been included following Grouper workshop on the 25th June, only stipulation is that the project upgrade is to the latest version of Grouper to ensure benefits of the functionality are available. BRD sign off to be confirmed by Service Management.
  • Additional 8 days requested/ approved by WIS  to cover A) Phase 2 delivery additional days required to cover :2 days for resolution of DEV SOA issues  and 1 day reqork for JIRAS B) Phase 3A early design work additional days required: 3 days for R & D work for Pull web Services due to 11g composite different to 10g, this is required before SDS can be started. This was reviewed and agreed by Business Lead, Senior Supplier and project team as required task for the project. and 2 days for peer rework activity not included in estimate. Increase resulting in current budget of 593 days increasing to 601 days.

      

Next Steps

  • Phase 2 Inbound ASOR sign off now expected 9th July
  • Phase 2 Inbound Deploy 16/17th July
  • Phase 2 Inbound DSOR / Closure
  • Phase 3A Pull Services and Upgrade Grouper commence Design

 

 

COM008

Migrate Exchange to Office 365

Discretionary

 

Milestones

 

 

 

 

 

 

 

RAG Status

RED

Report by Morna Findlay for June 2014

Achievements this period

 

Provisioning deployment review approved.

Incoming mail now flowing through new exchange servers.

Draft OLA passed to partners for review.

 

Outstanding Issues

 

Outgoing email not yet routed through new servers.

Live services to be decomissioned.

TAD to be completed.

New milestones to be agreed,

 

 

Next Steps

 

Estimate to create TEST envronment to be agreed.

TEST environment to be delivered.

Email lookup tool to be switched over to new provisioner.

New  milestones  to be approved.

OLA to be agreed with partners.

Procedures for migrating users between staffmail and office 365 to be tested and signed off.

Deployment review for migrations  to be held.

Deployment review for provisioner to be held.

Decomissioning work in TEST and LIVE to be carried out.

Deployment  review for decomissioning to be held.

 

Milestones

 

 

 

 

 

The project is RED as no estimate to complete work on the TEST environment is yet available and will not be till the retutn of devtech resources from annual leave.

 

 

WEB003

Mobile Information Solution With MyEd - Phase 1  

Compliance

 

Milestones

 

 

04-Aug-201411-Jun-2014Deployment Sign-off and Handover to SupportDeliver
11-Aug-201425-Jun-2014Phase 1 - ClosureClose

 

 

 

 

RAG Status

RED

Report by Maurice Franceschi for June 2014

 

As the project has been kept open to deal with more issues, the budget has increased beyond 10% and the project is now RED

Achievements in Last Period

  • DSOR signed off by project team, service owner and senior supplier but rejected by WIS

Issues

  • post-delivery issues being prioritised and resolved
  • new issues being raised agaimnst the project being dealt with
  • main problem is IDM TEST is not functioning so project budget now being used to fix IDM TEST Notifications so the project can complete the fixes
  • conflict with other projects

Next Steps

  • deployment sign-off and closure - if possible bring forward into 14/15

WEB005

Mobile Information Solution With MyEd - Configuration  

Discretionary

 

Milestones

18-Jul-201404-Jul-2014Sign-Off Build (Start of Term)
01-Aug-201425-Jul-2014Acceptance Sign-off of Deliverables for Start of Term
07-Aug-201430-Jul-2014Delivery (Musts for Start of Term)
15-Aug-201417-Jul-2014Deployment Sign-off (Start of Term)
30-Sep-201430-Sep-2014Sign-Off Design (Start of 2015) - TBC
28-Nov-201429-Aug-2014Sign-Off Build ( Start of 2015) - TBC
19-Dec-201426-Sep-2014Acceptance Sign-off (Start of 2015) - TBC
23-Dec-201402-Oct-2014Delivery (Start of 2015) - TBC
16-Jan-201509-Oct-2014Deployment Sign-off (Start of 2015) - TBC
30-Jan-201516-Oct-2014Closure

 

 

 

RAG Status

AMBER

 

 

Report by Maurice Franceschi for June 2014

 

The project remains on budget, scope and time to deliver the start of term functionality.

However, the project remains AMBER as directed by WIS to reflect the overall uncertainty about scope and budget in regard to the delivery for start of 2015.

 

Achievements in Last Period

  • Build during June and peer testing
  • Build sign-off (Early July) - Not Achieved. New milsetone set.

Issues

  • no issues of note

Next Steps

  • Build sign-off - mid July

 

 

CMW010

Document Management System (Serengeti) Upgrade

C

 

Milestones *

Revised mielstones yet to be confirmed with E&B and Finance

Target dateTitleStage
28-Feb-2014End of PlanningPlan
08-May-2014Build ReviewBuild
09-Jul-2014Integration ReviewIntegrate
17-Jul-2014Acceptance ReviewAccept
21-Jul-2014DeploymentDeliver
01-Aug-2014Deployment ReviewDeliver
08-Aug-2014ClosureClose

 

RAG Status

AMBER

Report by Tim Gray for June 2014

Achievements in Last Period

  • Serengeti's TEST upgrade completed
  • TEST configuration

Issues

  • A showstopper with the EBIS integration has not yet been resolved.
  • Agreement not yet reached with E&B or confirmed with Finance for revised LIVE upgrade (21/07/14)
  • Integration sign off delayed due to upgrade and post upgrade configuration issues
  • LIVE upgrade moved out due to other higher prioritised work (APPS LIVE DB Migration and IDM Upgrade)

Next Steps

  • Compete Integration testing
  • Complete UAT
  • Upgrade LIVE now w/c 21/07/14. Milestones to be re-planned when Serengeti confirm date

 

Project status amended to AMBER due to unresolved issues

 

COM011 (AP45-002)

New Visitor Registration System

Discretionary

 

Milestones

24-Mar-201424-Mar-2014Start of Project
04-Jul-201404-Jul-2014Foundations - Iteration 1
17-Jul-201417-Jul-2014Foundations - Iteration 2
18-Jul-201419-Jun-2014Project Brief
18-Jul-201427-Jun-2014End of Foundations Stage
12-Dec-201412-Dec-2014Delivery of Final Release
23-Jan-201523-Jan-2015Closure

 

(secured)

 

RAG Status

AMBER

 

 

 

Report by Maurice Franceschi for June 2014

 

As milestones beyond Project Brief are to be re-set, and the efffort estimate is currently higher than the bduget, the project is AMBER
  • Achievements in Last Period

  • resourcing for team confirmed - all roles filled
  • project brief rejected by WIS  

Next Steps

  • complete project Brief with estimates and booking confirmed
  • re-plan Foundations Phase as iterations
  • User Stories
  • Set up JIRA
  • TAD
  • Build Environments for Agile Development

 

 

AP34-035 CMW012

Election Count System Upgrade

Compliance

 

 

 

Milestones

Target dateTitle
04-Jul-2014End of planning
10-Jul-2014SDS
07-Aug-2014Build
26-Aug-2014ASOR
03-Sep-2014Deployment
09-Sep-2014DSOR
12-Sep-2014Closure

 

RAG Status

GREEN

 

Report by Sue Woodger for June 2014

 

Achievements

  • Demo of work completed held on 25 June. Everyone was happy with what has been produced so far
  • Project Brief signed off by team and submitted to WIS 4 July.

 

Issues

  • Was unable to secure resource for development until week beginning 7 July. This means the delivery date will be pushed out to 2 September causing a 9.5 day carry over into 2014/15. Project sponsor has agreed this carry over with programme manager (2/07/14).

 

Next Steps

  • Systems design starts on 7 July ans signed off on 11 July.
  • Build starts on 14 July

 

 

Project is green as plan agreed

 

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary

  

Project Code (AP Number)

Project Title

 

Discretionary/Compliance/Funded 

Report by [PM] 

This project was closed/withdrawn on dd-mmm-yy

[for closures] Please see the Completion Report / Closure Review for further information [include link]. 

[for withdrawn] Please see the PRICCL log for further details [include link].

 

COM006 (AP23-034)

CSE Reporting and Business Intelligence Optimisation

Discretionary

Report by Karen Stirling

This project was closed on 23-Sep-13

Please see the Completion Report for further information

WEB002

ECA CMS Technology

Funded

Report by Arthur Wilson

ECA have confirmed that they cannot commit to the second phase of the WEB002 project.  The second phase was originally planned to implement cosign and ldap integration for the new ECA drupal website. As a result, the project will be withdrawn from the 13/1/4 CMW programme.

Note that the phase 1 delivery of the basic drupal website for ECA will continue as a Service Management (RDS) task.

Project withdrawal

AP34-047

Discussion Forums Upgrade

The project was withdrawn during the mid-year review.

 

COM001

Office 365 for Students

Category:Discretionary

Report by Tim Gray

This project was closed on 28.02.14.

Please see the Completion Report for further information

AP34-037

Coldfusion 9 Upgrade for VRS

Project withdrawn.

CMW009

Video & Media Strategic Review

Discretionary

Report by Karen Stirling

This project was closed on 4th March 2014.

Please see the Completion Report for further information

WEB004

WIki Upgrade 

Compliance

Report by Morna Findlay

Project Closed - Completion Report

 

 

Section Five: New Approved Projects from 14/15 Annual Plan

Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.

 

 

Project InfoProject Managers Commentary

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies