Report for August 2015
- Report Date
- August 2015
Susan McKeown (IS Apps Programme Manager) for Zoe Lewandowski (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
HRS086 - CLOSED in August following the eRecruitment Board meeting on 11 August 2015. The Board approved the Upgrade plan and the Upgrade project is being requested to start in September as USG have confirmed funding HRS084 - GREEN - Project has been rescheduled and funding assigned HRS085 - GREEN - On track to deliver to budget and schedule HRS087 - GREEN - HR Reward Calculator In Year project added to programme. The development has been completed, an EQiA completed and published and UAT completed. Deployment scheduled for the end of November as is dependent on UMP010 successfully migrating the HR pages to EdWeb.
Resources
The 10 days showing as overbudget against AP56-049 have been moved from 15/16 into 16/17
Forward Look
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP56-025 HESA Staff Return 15/16 Compliance Planning - April 2016 Delivery - November 2016
RAG Status GREEN | Plan Plan to start end of March 2016 Dependencies
|
AP56-049 Enhancing Employment Technical Implementation Discretionary Planning - January 2016 Delivery - 2017
RAG Status GREEN | Plan Planned to start in December Dependencies Dependent on successful completion of HRS084 Enhancing Employment Analysis |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||
HRS084 (AP45-042)Enhancing Employment AnalysisCategory: Discretionary Milestones
Delivery - Nov 2015 RAG Status GREEN | Report by Franck Bergeret for August 2015 Achievements this Period
Issues
Next Steps
| ||||||||
HRS085 (AP45-063)HESA Staff Return 14/15Category: Compliance Milestones
RAG Status GREEN | Report by Anne Mathison for August 2015Achievements This Period
Issues
Next Steps
| ||||||||
HR Reward Calculator Category: Discretionary, Funded
Milestones
RAG Status GREEN | Report by Susan McKeown for August 2015 Achievements in This Period
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
HRS086 eRecruitment Proof of Concept Category: Discretionary, Funded | Report by Susan McKeown Project Closure Milestone achieved on 25-Aug-15 Project's Completion Report is available on the website. |