Report for December 2023
- Report Date
- December 2023
Report by Muriel Mewissen for Fiona Vine (portfolio Owner) and SCE programme stakeholders.
Section One: Programme Commentary, RAG and Resources Update
Commentary:
In December, there was no project active in this programme. Proposals for projects are being sought and prioritised within the Colleges.
The overall status for the SCE programme is GREEN.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
The start of year budget position is recorded in 2023/24 - Start of Year Programme Budget.
Forward Look - December 2023
Resources to end December 2023
Section Two: Projects Not Started
Project Info | Core Funding Budget Allocation |
---|---|
No project have been identified for start in 23/24 yet. Possible areas for proposals are:
|
SCE had a budget of 150 ring fenced days for 23/24. The following allocations were made:
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary |
N/A | There is currently no active project. |
Section Four: Closed or Withdrawn Projects
Project Info | Project Manager's Commentary |
---|---|
This project was started in February 2023 and was closed on the 6 October 2023. The Closure Report is available to view. |
Section Five: Programme Meeting Minutes
Date | Comments |
---|---|
17 November 2023 | Programme Review Monthly Meeting - November 2023 |
2 November 2023 | Programme Review Monthly Meeting - October 2023 |
19 September 2023 | Programme Review Monthly Meeting - September 2023 |
18 August 2023 | Programme Review Monthly Meeting - August 2023 |
20 June 2023 | Programme Review Monthly Meeting - June 2023 |
17 May 2023 | Programme Review Monthly Meeting - May 2023 |
18 April 2023 | Programme Review Monthly Meeting - April 2023 |
16 March 2023 | Programme Review Monthly Meeting - March 2023 |
15 February 2023 | Programme Review Monthly Meeting - February 2023 |
18 January 2023 | Programme Review Monthly Meeting - January 2023 |