November 2012
- Report Date
- November 2012
Report compiled by Nikki Stuart (IS Apps Programme Co-ordinator) for Karen Bowman (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
AP12-006 Evaluate Technical Implications of new eProcurement Scotland business solutions
Compliance Planning January 2012 Delivery May 2013 RAG Status GREEN
| Plan Start January with delivery May 2013.
Dependencies This project requires the eFinancials Upgrade to be completed before the Pecos/eFin interface can be upgraded. Planning could begin before the upgrade is completed.
The third party suppliers Amour and EBS need to finalise the required changes and updates required.
Support contracts expires in November 2013 and the upgrade must be completed before that date. |
AP12-019 Lean - Improved access to contract, supplier and product information
Discretionary
Planning February 2012 Delivery October 2013
RAG Status GREEN | Plan February start date with delivery by October 2013
Dependencies The launch of CCM on 1st October and the use of Hunter will impact this project |
AP23-014 Research Equiptment Procurement Asset Register
Compliance
Planning Sign Off - 5th October Delivery May 2013
RAG Status GREEN | Plan The planning phase is due for sign off on 5th October. The project is expected to deliver in May 2013.
Dependencies
|
AP23-015 eCommerce - Implementation
Compliance
Planning April 2013 Delivery December 2013
RAG Status GREEN | Plan
Dependencies eCommerce - Business Case will impact on the deliverables for this project. |
AP23-015 eCommerce - Infrastructure Changes
Compliance
Planning April 2013 Delivery December 2013
RAG Status GREEN | Plan
Dependencies eCommerce - Business Case will impact on the deliverables for this project. |
AP23-054 Purchase of Stock Using eProcurement Systems
<None>
Planning April 2013 Delivery July 2013
RAG Status GREEN | Plan
Dependencies
|
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | ||||||||||||
PPS001 (AP12-046) Enhancements to PSO
Category: Funded Milestones
RAG Status GREEN | Report by Susan McKeown for November 2012Achievements in Last Period
| ||||||||||||
PPS002 Research Equipment procurement Asset Register
Category: Compliance
Milestones
RAG Status: GREEN | Report by Morna Findlay for November 2012Achievements this period
Outstanding issues
Development resources cannot yet be requested or assigned until the business analysis is further advanced. Next steps
The project status has been set at GREEN.
| ||||||||||||
PPS003 eCommerce Services
Category: Compliance
Milestones
RAG Status: GREEN |
Report by Nikki Stuart for November Achievements this period
Issues
Next steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
Project Code (AP Number) Project Title
Discretionary/Compliance/Funded |