Report for February 2017
- Report Date
- February 2017
Section One:Programme Commentary, RAG and Resources Updates
Commentary
The programme remains in budget and as expected the burn rate has dipped now that eCommerce (PPS008) has closed and the ColdFusion Migrations (PPS009) is pending closure. The Procurement Journey online (PPS010) project was suspended in January awaiting the outputs from the Service Excellence Finance programme expected March/April.
Resources to end February 2017

Forward Look - February 2017

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|
|
|
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | ||||
|
PPS009 Procurement & Printing ColdFusion Migrations Compliance Milestones
RAG Status: AMBER
|
Report by Susan Duff for February 2017Achievements in Last Period
Issues
Next Steps
MilestonesClosure milestone to be revised. Was 17/2/17.
The project Status Amber due to the delay to closure. |
||||
|
PPS010 Procurement Journey and Online Training Discretionary Milestones Suspended
|
It was agreed that this project will be suspended awaiting the recommendations from the Finance Service Excellence programme. |
Section Four: Closed or Withdrawn Projects
| Project Info | Project Manager's Commentary |
|
PPS008 eCommerce - Implementation Compliance
|
Project Closure agreed January 2017 http://www.projects.ed.ac.uk/project/pps008/completion-report |
| Attachment | Size |
|---|---|
| 79.66 KB | |
| 90.17 KB |