Report for March 2018
- Report Date
- March 2018
Section One: Programme Commentary, RAG and Resources Updates
Forward Look

Resources

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|
AP78-025 Buy@Ed Enhancements Category: Discretionary
|
Due to start in April - PM allocated.
|
|
AP78-028 Decommision eCommerce Software Category: Compliance |
Withdrawal to be submitted April 2018 |
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary |
|
PPS010 Procurement Journey and Online Training Discretionary Milestones Suspended
|
It was agreed that this project will be suspended awaiting the recommendations from the Finance Service Excellence programme. |