Report for February 2019

Report Date
February 2019

Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate  (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

The Programme Commentary

Overall progress within the Programme is as follows :

  • RES069 - Upgrade of model now in test environment and awaiting testing of 5.12.4, concerns that business resource may not be able to test and deployment to live therefore may have to move out and will have a knock on effect to RIS007 being unsuspended as currently scheduled until mid April 2019 
  • RIS005 - ITT evaluation period has now completed and contract award pending, additional funding may be required to cover PM resource once full implementation plan is produced and an agreed date confirmed.
  • RIS006 - Progressing however some concerns around availability of testing resource due to commitments to Core Systems workshops therefore milestones may have to move
  • RIS007 - This project is now suspended until mid April 2019 as it has a dependency on RES069 delivering new project model to Live
  • RIS008 - project brief approved and analysis is underway however concerns around BA resource as currently on sick leave, review potential alternative options

 

Please find link to REF2021 Portfolio page.

 

AP89-027 GDPR for Pure project - agreed at previous Programme review that we will initiated this project however will review proposal document for any further information to be included to aid planning

Discussion underway around Pure Cloud Portal.

Overall Programme RAG: AMBER

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 

 

 Section Two: Projects Not Started

Project Info Project Manager's Commentary
AP078-29 PURE Research Explorer- replace with new module from Elsevier Project not started yet, earliest start date would be March 2019
AP89-026 Support for REF proposed at last Programme meeting to request placing this project and budget into 19/20
AP89-027 GDPR for Pure Project not started yet, possible start date March 2019

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

RES069 PURE UPGRADE TO NEW PROJECT MODEL

Compliance / Core & Sponsor Funded

Milestones

Milestone Due Date Complete
Integration - Upgrade to Pure v5.12.4 & UPM Complete (TEST) 20-Mar-2019 No
Upgrade to PURE 5.12.4 & UPM Complete (LIVE) 26-Mar-2019 No
DSOR 5.12.4 & UPM Complete 09-Apr-2019 No
Closure 23-Apr-2019 No

RAG Status:  AMBER

 

 

Report by Kim Keenan for February 2019

Activities completed
  • Implementation plan has been updated to detail changes from DEV
  • TEST has been upgraded to 5.12.4 and UPM has been implemented
  • PICCL 20 has now been approved by the business and WIS

Issues

  • The business have not agreed a Go Live date and testing has not commenced yet
Next Steps
  • Complete Test Plan
  • Commence UAT of 5.12.4

The project status is AMBER on the basis that the business have not agreed a Go Live date and testing has not commenced yet.

 

 
 
 

 

 

 

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
Procurement Complete 29-Mar-2019
Build & Configure Complete (DEV) 16-Jul-2019
Acceptance Complete (TEST) 27-Aug-2019
Deployment Complete 05-Sep-2019
DSOR 19-Sep-2019
Project Closure Complete 17-Oct-2019

RAG Status : AMBER

 

 

Report by Kim Keenan for February 2019

Achievements in Last Period
  • ITT responses returned

  • Supplier Demonstration(s) have been undertaken

  • ITT has been scored accordingly

  • Business and technical consensus meetings have been held and scored accordingly following supplier demonstration

Issues
  • The project being over budget, the original estimate was 50 days however this is now looking at 63 days which needs to be discussed with the Project Sponsor.
Next Steps
  • Award contract
  • Agree contentious points with preferred supplier
  • Agree Implementation Plan

The project status is AMBER this is due to the project being over budget, the original estimate was 50 days however this is now looking at 63 days which needs to be discussed with the Project Sponsor.

RIS006 Worktribe Upgrade V3

Compliance / Core Funded

Milestones:

Milestone Due Date
Worktribe Upgrade v3 Complete in LIVE 12-Mar-2019
Worktribe v3 DSOR Complete 26-Mar-2019
Closure 04-Apr-2019

RAG Status : AMBER

 

 

Report by Kim Keenan for February 2019

Achievements in Last Period
  • WT DEV environment upgraded to latest patch 3.0.434

Issues
  • UAT has still to be completed and date for upgrade to Live to be agreed
  • Milestones to be revised
Next Steps 
  • WT TEST environment upgraded to latest patch 3.0.434
  • Test Plan Developed
  • UAT commences

 

The project status is AMBER - UAT has still to be completed and date for upgrade to Live to be agreed

RIS007 PURE Upgrades v5.13 to 5.15

Compliance / Core Funded

Milestones:

Milestone Due Date
Upgrade to Pure 5.13.4 DEV Complete 28-May-2019
Upgrade to Pure 5.13.4 TEST Complete 09-Jul-2019
Upgrade to Pure 5.13.4 DSOR 08-Aug-2019
Upgrade to Pure 5.13.4 LIVE Complete 08-Aug-2019
Upgrade to Pure 5.14 DEV Complete 21-Aug-2019
Upgrade to Pure 5.14 TEST Complete 10-Sep-2019
Upgrade to 5.14 DSOR Complete (LIVE) 07-Oct-2019
Upgrade to 5.14 LIVE Complete 07-Oct-2019
Upgrade to 5.15 DEV Complete 23-Oct-2019
Upgrade to 5.15 TEST Complete 13-Nov-2019
Upgrade to 5.15 DSOR Complete (LIVE) 10-Dec-2019
Upgrade to 5.15 LIVE Complete 10-Dec-2019
Closure 17-Dec-2019

 

RAG Status: SUSPENDED

 

Report by Kim Keenan for  February 2019

Achievements in Last Period
  • This project has been suspended awaiting completion of RES069
Issues
  • There are no issues to report at this stage
Next Steps 
  • Unsuspend project and commence Pure upgrades

 

The project status is SUSPENDED until mid April 19

 

 

 

 

 

RIS008 REF2021 Data Requirements Analysis

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
Enterprise Architecture Document 22-Mar-2019
Options Paper Complete 22-Mar-2019
Delivery Complete 08-Apr-2019
Project Closure Complete 24-Apr-2019

RAG Status : GREEN

Report by Kim Keenan for February  2019

Achievements in Last Period
  • Further business meetings held to determine their initial business requirements and define the "As Is" and "To Be" Processes

  • Project Brief approved by the business and WIS

Issues

  • There are no issues to report this month

Next Steps 

  • As Is and To Be business processes to be defined and documented
  • Business Requirements Document produced
  • Options paper produced
  • Enterprise Architecture produced

The project status is GREEN

 

 

 

Other Research projects outwith the RIS programme:

This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner

STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements 

Discretionary / Sponsor funded

Milestones

Provisional  milestones updated on Projects website, will need updated after re-plan, once scope change approved

Target Date Title
   

RAG Status : SUSPENDED

 

 

Report by Jamie Thin for February 2019
 
Achievements in Last Period
  • Project currently suspended
  • Closure / withdrawal meeting planned for 6th March however delayed due to PM sick leave this will be rescheduled
Issues
  • Project manager working on SEP priority project therefore delay in withdrawing project
Next Steps 
  • Project will be withdrawn in due course during March 2019
 

 

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
RIS003 Pure Upgrade v5.10 to v5.12

Report by Kim Keenan

Completion Report

This project closed 17th August 2018

 

RIS004 Worktribe Upgrades - Readiness for GDPR

 Report by Kim Keenan

Completion report

This project closed 21st September 2018