November 2017

Report Date
November 2017

(Draft) SMI Programme Report compiled by Colin Watt (IS Apps Programme Manager) for Programme Owners Neil  Bruce and Alex Carter

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

 

Overall Programme RAG: AMBER

 

Forward Look and RAG

 

 

Resource Summary

 

Section Two: Projects Not Started

No Projects outstanding.

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

SMI018 (AP67-042)

UniDesk Annual Upgrade

Category: Compliance

Milestones

22-Dec-2017 Integration Testing sign off
23-Jan-2018 Acceptance Testing Sign Off - Edinburgh
25-Jan-2018 Begin UAT on St Andrews, Stirling, Abertay, Sheffield Hallam, Ulster, Edinburgh Napier, Durham
31-Jan-2018 Deploy to LIVE - Edinburgh
12-Feb-2018 End UAT on St Andrews, Stirling, Abertay, Sheffield Hallam, Ulster, Edinburgh Napier, Durham
21-Feb-2018 Begin Deployments to institutions
18-Apr-2018 End of Deployments to institutions
02-May-2018 Deployment Sign Off
09-May-2018 Closure

RAG Status: 

AMBER

 

Report by Chris Konczak for November 2017

Achievements in Last Period

  • QuickCalls integration and testing with the API card number reader completed
  • DEV environment signed off
  • Institution builds on TEST have commenced and progressing well for the training scheduled on 11/12/2017. Project team, along with the institutions have agreed a scheduled upgrade of TEST below:

TEST Upgrade - Agreed Dates

Member

Tuesday 28th November

Edinburgh - completed

Friday 1st December

Abertay / Stirling - completed

Monday 4th December

 

Tuesday 5th December

 

Wednesday 6th December

Napier/ Sheffield Hallam/St. Andrews

Thursday 7th December

 

Friday 8th December

 

 

Issues

 

  • Durham has told us they have a scheduled programme of work that requires access to their UniDesk TEST environment until January 2018. They have not given us permission to upgrade their TEST environment in December
  • Cost is Amber

Next Steps​

  • QuickCalls and Shibboleth integration tested and completed.
  • All TEST environments ready for training in December
  • Integration testing signed off

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

SMI013 (AP56-009)

UniDesk Annual Upgrade

 

Closure Approved 03/11/17
AttachmentSize
Image icon smi-forwardnov17.jpg82.62 KB
Image icon smi-effort-nov17.jpg106.75 KB