Report for August 2025

Report Date
August 2025

Section One: Programme Commentary, RAG and Resources Update

Commentary

Programme status: The overall status of the STU programme for August 2025 is AMBER due to the RED status of the Student Counselling project and the programme does not have a confirmed budget for 25/26.

Project Highlights

  • STU273: GREEN - The Review went live and although some issues were encountered, the team resolved quickly
  • STU274: RED - This is a secure project so only those with access can view the August report.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

Forward Look - August 2025

Resources to end August 2025

Section Two: Projects Not Started

N/A - All projects are delivered or in progress

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

STU273 Making Transitions Personal Review 25/26

Category: Discretionary

Milestones

Milestone Due Date
Review reminder email sent to students 09-Sep-2025
Review closes 19-Sep-2025
Review Recommendations' email sent to students 28-Oct-2025
Delivery Sign-Off Review 06-Nov-2025
Closure (Major Milestone) 20-Nov-2025

RAG Status:

GREEN

Report by Alexandra Mezeul for August 2025

Achievements this Period

  • Finalised the organisational hierarchy changes
  • Set the Review to Live - went out in Welcome Email from Schools between 19th-21st August

Issues

  • There was an oversight by the SharePoint Technical Lead / Service Owner who did not activate the SharePoint Student Groups for permission/access to students on the day the MTP Review went live - 19th August. There were multiple issues raised on the 19th August on access issues by students and logged into a Problem Log - P2508-019. This log noted a resolution by the SharePoint Lead in the late morning of 20th August.  For more details please review the issue link below.

  • There was also an issue with the SharePoint dashboard which required additional effort to correct. This issue was the way completed surveys were displayed on the dashboard as both some schools were not visible and the real submitted number of Reviews was not shown. The Development Lead was able to resolve these issues, but an additional 1 day was used.
  • There were issues with the cron job which runs the automatic updates for newly provisioned accounts for students and includes them in the MTP SharePoint site. The issue was logged here: I250812-4117. The cron was working fine when triggered manually, but there was an issue with the mtpapi which was resolved within 3 days of discovery.

Next Steps

  • Send the Reminder email to students on the 9th September
  • Close the Review on 19th September
  • Conduct Reflections exercise after Review Closure

STU274 Student Counselling Coldfusion Replacement

Category: Discretionary

RAG Status:

RED

 

Report by John Dawes for August 2025
This is a secure project so only those with access can view the August report.

Section Four: Closed or Withdrawn Projects

Only those projects closed from July 2023 onwards are included in this table. A full history of completed projects is available on the programme's website.

Project Info Project Manager's Commentary
STU270 Careers Service Operating Platform Project closed in  July 2023. The Closure Report is available.
STU268 Making Transitions Personal  Project closed in June 2024. The Closure Report is available.
STU269 Student Case Management System Project closed in July 2024. The Closure Report is available.
STU272 Making Transitions Personal Review 24/25 Project closed in November 2024. The Closure Report is available.
STU271 Prospective Student Web Future State Project closed in February 2024.
Programme Status
Has formal escalation taken place?
No