Integrate

Current project status

Report Date RAG Budget Effort Completed Effort to complete
March 2025 GREEN 0.0 days 0.0 days 0.0

Room Ins and Outs to cover the RAAC contingency spaces.

 

McEwan Hall Foyer 1,2,3 &4

McEwan Hall Robing Room

 

What happens to the Semester 1 contingency rooms?

Current project status

Report Date RAG Budget Effort Completed Effort to complete
March 2025 GREEN 0.0 days 0.0 days 0.0

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2024 GREEN 0.0 days 0.0 days 0.0

LT1, LT2 and LT3 are getting their ceilings replaced. This impacts the projection and cameras. We will also need to change the Front of House (FoH) speakers as we lose the ceiling speakers.

LT4 & LT5 Complete upgrade with LED videowall, speakers etc.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
March 2025 GREEN 0.0 days 0.0 days 0.0

North East Building J.03 - Complete

North East Building J.03 - Complete

Hunter Building R.02B - Waiting on RAAC to be fixed

Current project status

Report Date RAG Budget Effort Completed Effort to complete
September 2023 GREEN 0.0 days 0.0 days 0.0

 

 

Reference (From BRD)                                    

Scenario / Acceptance Criteria                       

Tested By                      

Date Tested                  

Outcome Pass/Fail                

Notes                        

 

 

Reference (From BRD)                                    

Scenario / Acceptance Criteria                       

Tested By                      

Date Tested                  

Outcome Pass/Fail                

Notes                        

 

 

Reference (From BRD)                                    

Scenario / Acceptance Criteria                       

Tested By                      

Date Tested                  

Outcome Pass/Fail                

Notes                        

 

 

Reference (From BRD)                                    

Scenario / Acceptance Criteria                       

Tested By                      

Date Tested                  

Outcome Pass/Fail                

Notes                        

 

 

Reference (From BRD)                                    

Scenario / Acceptance Criteria                       

Tested By                      

Date Tested                  

Outcome Pass/Fail                

Notes