Integrate

Current project status

Report Date RAG Budget Effort Completed Effort to complete
March 2024 GREEN 0.0 days 0.0 days 0.0

North East Building J.03 - Complete

North East Building J.03 - Complete

Hunter Building R.02B - Waiting on RAAC to be fixed

Current project status

Report Date RAG Budget Effort Completed Effort to complete
September 2023 GREEN 0.0 days 0.0 days 0.0

New build at the BioQuarter.

1x "Events/Teaching :-( Space" 170 seater

1x Seminar room that can split into 2

Some Innovation and Outreach space

1x Stoop open performance area

Various meeting rooms

Current project status

Report Date RAG Budget Effort Completed Effort to complete
March 2024 GREEN 0.0 days 0.0 days 0.0

THIS IS A SECURE PROJECT. PLEASE DO NOT PUBLISH.

 

The University of Edinburgh procured hardware, software and services to replace the majority of its data network infrastructure, including the current ResNet network which services the University's residential estate operated by Accommodation, Catering and Events (ACE).

Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2023 AMBER 484.0 days 986.3 days 397.2

AV for refurbished building over several floors.

 

Opening is May 2022. :-)

Current project status

Report Date RAG Budget Effort Completed Effort to complete
March 2024 AMBER 0.0 days 0.0 days 0.0

 

 

Reference (From BRD)                                    

Scenario / Acceptance Criteria                       

Tested By                      

Date Tested                  

Outcome Pass/Fail                

Notes                        

 

 

Reference (From BRD)                                    

Scenario / Acceptance Criteria                       

Tested By                      

Date Tested                  

Outcome Pass/Fail                

Notes                        

 

 

Reference (From BRD)                                    

Scenario / Acceptance Criteria                       

Tested By                      

Date Tested                  

Outcome Pass/Fail                

Notes                        

 

 

Reference (From BRD)                                    

Scenario / Acceptance Criteria                       

Tested By                      

Date Tested                  

Outcome Pass/Fail                

Notes                        

 

 

Reference (From BRD)                                    

Scenario / Acceptance Criteria                       

Tested By                      

Date Tested                  

Outcome Pass/Fail                

Notes