Project Brief

Document Sign Off

Name Project Role Date Signed Off
Dominic Tate Project Sponsor 19/11/2021
Karen Stirling Project Manager / Programme Manager 19/11/2021
Damon Querry RIS Business Lead  
Nik Hussin RIS Team  
Suran Perera / Stuart Craig Application Management  
Mark Lang Development Technology Info
Emma McNab P&M Integrations 11/11/2021
Billy Wardrop LTW WAC Team  
Chris Cord Technology Management Info
John Allison Software Development Info - 18/11/2021

 

 

For guidance on how to complete the Project Brief template, please click here.

For staff in Information Services Group (ISG), please click here for guidance on how to complete the Project Brief following ISG guidelines. 

Project Info

Project
Pure Upgrades v5.22 to v5.24
Code
RIS022
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
21-Oct-2021
Planning Date
12-Nov-2021
Delivery Date
28-Sep-2022
Close Date
14-Oct-2022
Programme Priority
1
Overall Priority
Normal
Category
Compliance