STU218 - covers externally-driven enhancements, it was started during 2011-12, and will close once the last Phase - Phase 5 - ATAS is delivered by the end of Nov 2012

Update 7-Nov 2012

 

Now moving to Closure

Phase 5 - Recording  ATAS certificates - deployed to LIVE on 6-Nov 2012 - Done

Previously Delivered

Phase 1 - ATAS changes went LIVE on Tues 17-Jan 2012- Done

Phase 3 - UKBA ELTC Students - went LIVE on 31/08/2011 - Done

Phase 4 - Medical Electives - went LIVE on 10-July-12 - Done

 

N.B. this project was started before the move to the new projects website, so documentation is only shown from 6th August 2012.   Documentation prior to this can be found on the old site at http://www.projects.ed.ac.uk/areas/student/sacs/STU218/index.shtml

 

 

Project Info

Project
SACS Small-Scale enhancements - External
Code
STU218
Programme
Student Systems Partnership SSP
Project Manager
Jamie Thin
Project Sponsor
Bruce Johnson
Current Stage
Close
Status
Closed
Start Date
21-Nov-2011
Planning Date
n/a
Delivery Date
n/a
Close Date
07-Dec-2012
Overall Priority
Normal
Category
Discretionary

Documentation

Not available.

Project Dashboard

Reporting

Nothing to report.

Project journal

No entries found.

Change dashboard

Nothing to report.