Impact

Priority and Funding

This project has an overall priority of 2. It is a discretionary, funded project within the USG portfolio. The project is funded in a 50:50 split between the Careers Service and Development & Alumni.

 

Impact and Dependencies

This project will impact on the subsequent implementation project, for which this project will define the plan. If this project is delayed, there is a risk that the implementation project will also be delayed.

 

Project Risks

 

Ref Title Impact Probability Risk Status Risk Owner Date of Last Review  
1 The assumption that GDPR drivers for delivering the solution ASAP is not valid Medium Medium AMBER Open Grant Spence 28-Apr-2017

view

2 Scope expands to include more than support for Simon Medium Low GREEN Open David Watters 28-Apr-2017

view

3 The required support staff / academic staff / alumni / students will not be available over the summer to participate in the tender evaluation Medium Medium AMBER Open Simon Raeside 28-Apr-2017

view

4 Business/functional requirements are not well understood and readily translatable into procurement requirements Critical Medium AMBER Open David Watters 28-Apr-2017

view

6 Technology requirements are not covered by the existing ISG Procurement Question Sets High Medium AMBER Open David Watters 28-Apr-2017

view

7 There are no mature software solutions in the market that do what we need Critical Low AMBER Open Simon Raeside 28-Apr-2017

view

8 Engagement with the communications will not be carried out by D&A and Student Services through existing channels Medium Low GREEN Open David Watters 28-Apr-2017

view

9 Delays to procurement will cause delay to implementation project Medium Medium AMBER Open David Watters 02-Jun-2017

view

 

Project Info

Project
Student Alumni Platform Procurement (USG005)
Code
USG005
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Grant Spence
Current Stage
Close
Status
Closed
Start Date
27-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
19-Jan-2018
Programme Priority
2
Overall Priority
Normal
Category
Discretionary