Report for March 2018
- Report Date
- March 2019
Achievements
-
Migration is complete
Issues
- None
Next steps
- Go live
- Project closure
Milestones
Plan | End of Planning | 09-Mar-2018 | 02-Mar-2018 |
Build | Build Complete | 15-Jun-2018 | 01-Jun-2018 |
Integrate | UAT Complete | 21-Dec-2018 | 18-Jul-2018 |
Accept | Migration | 28-Feb-2019 | 03-Aug-2018 |
Deliver | Go Live | 29-Mar-2019 | 06-Aug-2018 |
Close | Closure Report | 12-Apr-2019 | 28-Sep-2018 |
- Approved budget
- 28.0 days
- Activity this month
- 0.0 days
- Activity this year
- 4.2 days
- Activity to date
- 26.7 days
- Estimate to complete current year
- 1.1 days
- Estimate to complete future years
- 0.0 days