Report for March 2018

Report Date
March 2019

Achievements

  • Migration is complete

Issues

  • None

Next steps

  • Go live
  • Project closure

Milestones

Plan End of Planning                    09-Mar-2018               02-Mar-2018
Build Build Complete 15-Jun-2018 01-Jun-2018
Integrate          UAT Complete 21-Dec-2018 18-Jul-2018
Accept Migration 28-Feb-2019 03-Aug-2018
Deliver Go Live 29-Mar-2019 06-Aug-2018
Close Closure Report 12-Apr-2019 28-Sep-2018

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
28.0 days
Activity this month
0.0 days
Activity this year
4.2 days
Activity to date
26.7 days
Estimate to complete current year
1.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Legal Services Document Management System Migration
Code
USG011
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
Geoff Cropley
Project Sponsor
Lindsay Hampton
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
20-Feb-2018
Planning Date
09-Mar-2018
Delivery Date
19-Apr-2019
Close Date
26-Apr-2019
Overall Priority
Higher
Category
Discretionary