AP45-003

Annual project to deploy a call centre to provide support for SQA and A Level results days admission queries and Clearing 2025.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2025 GREEN 50.0 days 39.0 days 6.0

Project Info

Project
Results Days and Clearing Helpline 2025
Code
USG029
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
Ailsa Glass
Project Sponsor
Katrina Castle
Current Stage
Execute
Status
In Progress
Start Date
10-Feb-2025
Planning Date
05-Jun-2025
Delivery Date
15-Aug-2025
Close Date
26-Sep-2025
Overall Priority
Higher

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.