Report for April 2021

Report Date
April 2021

Achievements this period

  • The project has been initialed
  • Project website created

Issues

  • A Project Manager has not yet been assigned

Next Steps

  • Start and complete project planning after project manager is assigned

RAG

  • AMBER: The RAG is Amber as a project manager has not yet been assigned. The proposed PM does not have capacity to pick this up.
Project Status
RAG Status
Overall
AMBER
RAG Commentary
AMBER: The RAG is Amber as a project manager has not yet been assigned. The proposed PM does not have capacity to pick this up.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation