Monthly Progress Report

Report Date
May 2015

Achievements in last period:

  • Initiation of project
  • Project manager assigned
  • Project website set up
  • Estimation of In-year project agreed
  • Agreed project will run over to 15-16

Issues:

  • None

Next Steps:

  • Discussion with Seniour User
  • Draft Brief completed
  • Brief approved
  • Established contact with supplier

Milestones:

Milestone DateMilestone Stage
15-Jun-2015Planning
01-Jul-2015Business Analysis
22-Jul-2015Systems Design
03-Aug-2015Installation Build
17-Aug-2015Integration
14-Sep-2015Acceptance
30-Sep-2015Deployment
30-Oct-2015Closure
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
60.0 days
Activity this month
0.8 days
Activity this year
2.1 days
Activity to date
2.1 days
Estimate to complete current year
26.6 days
Estimate to complete future years
33.0 days

Project Info

Not available.

Documentation

Not available.