June Progress Report

Report Date
June 2015

Achievements

  • Brief wriitten and agreemnt underway
  • Inital calls taken place with our supplier
  • Business Analysis underway
  • Technical investigation underway

Issues:

  • None

Next Steps:

  • Brief approved
  • Analysis complete
  • TAD complete
  • Systems Design complete
  • VM Servers ordered

Milestones:

Milestone DateMilestone Stage
29-Jun-2015Planning
06-Jul-2015Business Analysis
28-Jul-2015Systems Design
14-Aug-2015Installation Build
31-Aug-2015Integration
21-Sep-2015Acceptance
08-Sep-2015Deployment
16-Oct-2015Closure
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
60.0 days
Activity this month
6.9 days
Activity this year
9.0 days
Activity to date
9.0 days
Estimate to complete current year
13.3 days
Estimate to complete future years
37.5 days

Project Info

Not available.

Documentation

Not available.