Monthly Progress Report

Report Date
October 2015

Achievements:

  • Finance have clarified the DNS information that Bottomline required
  • Discussed getting HSM set up to wait until Networks are ready before it will be connected
  • Planned Bottomline to be on site to set up HSM's - 5-Nov
  • Now making progress with Networks currently establishing the days when this can take place
  • Finance, Bottomline and IS Apps have provided the information that Bottomline require

Issues:

  • None

Next Steps:

  • Production, Finance and IS Apps agreed 24 Nov is when the ITI VM Servers can take place
  • Following this the VM Servers can be set up with HSM
  • Bottomline re HSM on site 5 Nov to set up HSM's although not connected at this stage
  • Agree plan for Bottomline 3 day visit - 1-3 Dec to set up TEST, where Test checked out for 2 days and Finance training takes place 3 Dec.
  • Agree plan for Bottomline to set up LIVE agree with Finance
DateMilestone
04-Dec-2015Installation / Integration
08-Dec-2015Acceptance
10-Dec-2015Deployment
16-Dec-2015Deployment Sign Off Review (DSOR)
07-Apr-2016Closure
07-Apr-2016Decommission Albacs

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
80.5 days
Activity this month
2.8 days
Activity this year
25.2 days
Activity to date
43.8 days
Estimate to complete current year
32.4 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.