Monthly Report

Report Date
March 2016

Achievements:

  • Deployment sign off review (DSOR) was successfully completed at end of February
  • Live CSeries continues as normal activity, all files have been sent  apart from instances where new set up required. The procedures set up have been well proven
  • HSM password set up and use is proven every time a payment is required. Only 1 from 11 HSM user remains to be set up, but SAS Finance have that in hand (at 1/4)

Issues

  • None

Next Steps:

  • Decommission Albacs
  • Complete Albcas Closure

Project has been smoothly progressing with all work being completed by SAS Finance. Once decommissionned Albacs the project can be closed

Milestones

DateMilestone
05-May-2016Closure
05-May-2016Decommission Albacs
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
81.0 days
Activity this month
1.0 day
Activity this year
55.0 days
Activity to date
74.0 days
Estimate to complete current year
6.0 days
Estimate to complete future years
0.0 days