Monthly Progress Report

Report Date
May 2016

Achievements:

  • 3 months successfully running with C-Series
  • Decommissioned Albacs
  • Tidy up of Albacs completed and removal from servers
  • Completed Albcas Closure
  • Albacs Replacement Closure to WIS 3-Jun-16

Issues

  • None

Next Steps:

  • Project Closed
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
81.0 days
Activity this month
5.0 days
Activity this year
61.0 days
Activity to date
80.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days