Report for March 2018

Report Date
March 2018

Achievements

  • Consultation workshop was held with selected business partners, who confirmed overall business requirements 
  • The defined business requirements were approved by the project team
  • A demonstration of a potential solution, Safety Health Environment was held on 3rd April as part of the early market engagement process
  • Discussions were held with the Estates Programme Manager regarding the scheduling of a demonstration of selected Archibus WebCentral modules. As a result a revised project plan was prepared and circulated for review
  • Project handover to the new project manager, Lee-Ann Simpson commenced

Issues 

  • The business lead has expressed concerns regarding a potential delay to reviewing the Archibus WebCentral modules and the impact of the project being extended by four week. This is currently being reviewed

Next Steps 

  • Confirm revised project plan
  • Complete gap analysis review with regards to 
    • existing Archibus modules
    • potential market supplied solutions  
  • Commence business report
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Change: Project delivery will be delayed by 4 weeks to enable the scheduling of selected Archibus WebCentral modules demonstration by the supplier. This has been approved by the project team and sponsor
Change Status
Activity
Approved budget
50.0 days
Activity this month
3.1 days
Activity this year
29.8 days
Activity to date
29.8 days
Estimate to complete current year
22.9 days
Estimate to complete future years
0.0 days